Development of Prolez Wind Farm

Prolez Wind Farm will be located in the northeastern part of Bulgaria, to the southwest from village of Prolez, Shabla region.

The planned total output of the wind farm is 80 MW. The connection of wind farm Prolez to 110kV transfer grid will be implemented through building of step-up substation, located within the area of the wind farm and breaking down of 110kV air transmission line Dropla.

The connection to the 110kV transmission grid of the installed capacity is agreed officially with the Bulgarian National Electrical Company and with the Bulgarian Transmission Grid Operator and a Final Contract for connection of the whole farm to the 110kV transmission gGrid was signed.

The implementation of the project is scheduled for the following two stages:

  • First stage- installation and commissioning of wind turbine generators with total installed capacity of 40 MW. Construction and commissioning of 20/110kV step-up substation. 
  • Second stage- installation and commissioning of wind turbine generators with total installed capacity up to 40 MW. 

At the current moment Nimex-2004 Ltd owns nineteen sites for installation of wind generators and one more site for 20/110kV substation, which have a changed status - sites for electricity generation.

Detail design for construction of 20/110kV step-up substation is agreed with NEC EAD.